Archives

Deralok 2 hydro power plant

Deralok 2 hydro power plant

Specification: Capacity: 37.6 MW (2 Units of 18.8 MW) Type of power house: Surface Main equipment: Turbine: Vertical Kaplan, 142.8 rpm Generator: Synchronous type, 11 KV Governor: Digital electronic frequency governors, 60 bar Crane: One power house main crane, 150 tons Role of Farab Equipment Manufacturing Co. Design, material supply, manufacturing management and installation of [...]
Read more
Tehran urban railway line 7

Tehran urban railway line 7

General Specification: Length: 26 km Type: Underground Passenger stations: 22 Line capacity: 45,000 passengers per hour per direction Headway: 120 sec. Main equipment: Rolling stock: 100 train sets Depot equipment & auxiliary vehicle Signaling system Control & SCADA & BMS Communication system Automatic fare collection (AFC) Power supply included: Traction rectifier substation (TRS): 18 units [...]
Read more
Utility and offsite units of Bushehr Petrochemical Complex

Utility and offsite units of Bushehr Petrochemical Complex

Engineering of utility & offsite units of Bushehr Petrochemical project, Phases 2 &3 and engineering procurement support, Consist of:  Water treatmnet, cooling towers unit, air and nitrogen unit, steam generation unit  Fire fighting system  Piping interconnecting  Electric power distribution, emergency diesel generator, telecom, control & instrumentation  Buildings (substation, control, workshop, secuirity, firefighting, etc)  Storage tanks

Read more
South pars steam turbine power plant and water desalination plant

South pars steam turbine power plant and water desalination plant

Power plant specification: Capacity at ISO conditions: 480MW (3 Units of 160 MW) Fuel type: Natural gas Grid voltage: 400 KV Site conditions: Altitude: 100 m.a.s.l Ambient temperature: 2-48° C Relative humidity: 65 - 100% Water desalination specification: Design capacity: 8,000 m3/day No. of units: 3*2,667 m3/day Sections: See water intake: Sea water transfer pumps [...]
Read more
Terem hydro power plant

Terem hydro power plant

Specification: Capacity: 5.2 MW (2 Units of 2.6 MW) Type of power house: Surface Main equipment: Turbine: Vertical Pelton, 750 rpm Generator: Synchronous type, three phase 3.3 KV Butterfly valve: 0.7 m inner outlet diameter Governor: Hydraulic power unit, 250 bar Transformer: Three phase step up transformers, 33 KV, 3 MVA Crane: One power house [...]
Read more
Sardasht hydro power plant

Sardasht hydro power plant

Specification: Capacity: 150 MW (3 Units of 50 MW) Type of power house: Surface Average annual power generation: 422 GWh Main equipment: Turbine: Horizontal Francis, 428 rpm Generator: Synchronous type, 13.8 KV Butterfly valve: 2.6 m inner outlet diameter Governor: Electrohydraulic type governors, 60 bar Transformer: Three phase step up transformers, 132 KV, 60 MVA [...]
Read more
Azad pumped storage power plant

Azad pumped storage power plant

Specification: Capacity: 510 MW (3 Units of 170 MW) Type of power house: Underground Main equipment: Turbine: Vertical Francis pump-turbine, rated 500 rpm, 2 with single speed and 1 with variable speed Generator: 2 synchronous and 1 double-fed asynchronous, each of 185 MVA, 15.5 KV Inlet valve: 3 spherical type Governor: 3 electro-hydraulic governors for […]

Read more
Pardis petrochemical Complex (Phase 3- Ammonia & Utility)

Pardis petrochemical Complex (Phase 3- Ammonia & Utility)

Pardis Petrochemical Complex Project has been defined to perform mechanical erection, pre-commissioning and assisst in comissioning of units & packages of Amonia and Offsite Units. Role of Farab Construction Co. Installation and precommissioning of electromechanical equipment
Read more
Azad water conveyance tunnel

Azad water conveyance tunnel

Specification: Type of tunnel: Mechanized concrete tunnel for water transfer Capacity: 5 m3/sec. passing flow Main volume: Precast concrete segment: 54,200 pieces in 9,034 rings, each ring consist of 6 segments Concrete volume: 35,000 m3 including lining and grouting Reinforcement: 1,800 tons Open excavation volume: 550,000 m3 Tunnel excavation volume: 120,000 m3 in hard and […]

Read more