Project Info
  • Client: Tehran Urban & Suburban Railway Operation Co.
  • Main Contractor: Farab
  • Location: Tehran, Iran
  • Scheme: EPC
  • Scope: Electromechanical equipment
  • Progress: Under construction
  • General Specification:
    • Length: 26 km
    • Type: Underground
    • Passenger stations: 22
    • Line capacity: 45,000 passengers per hour per direction
    • Headway: 120 sec.
  • Main equipment:
    • Rolling stock: 100 train sets
    • Depot equipment & auxiliary vehicle
    • Signaling system
    • Control & SCADA & BMS
    • Communication system
    • Automatic fare collection (AFC)
    • Power supply included:
      • Traction rectifier substation (TRS): 18 units
      • Lighting & power substations (LPS): 52 units
      • Third rail system: 76 km
    • Ventilation
    • Fire alarm system
    • Fire extinguishing system
    • Escalators
    • Elevators

Role of Farab Equipment Manufacturing Co.

  • Material supply and local manufacturing management of 32 diffusers

Role of Farab Construction Co.

  • Installation of electromechanical equipment

Related News

Enter your keyword