Yala1 hydro power plant

portfolio
portfolio
Project Info
  • Client: Gichuki Venture
  • Main Contractor: Farab
  • Location: Kenya
  • Scheme: EPC
  • Scope: Electromechanical & hydromechanical equipment, power house civil works, weir and waterway
  • Progress: Under construction
  • Specification:
    • Capacity: 10 MW (2 Units of 5 MW)
    • Values per Unit:
      • Nominal net head (HN): 40.0 m
      • Gross head (HB): 45.0 m
      • Nominal discharge (QA): 14.0 m³/s
      • Max. discharge (Qmax): 14.7 m³/s
      • Nominal Turbine Output (PTnom): 5074 kw each
      • Max. Turbine output (PT): 5227 kw each
      • Turbine speed (n1): 428.57 rpm
      • Runaway speed (nD): 1018 rpm
      • Runner outlet diameter (D2): 1380 mm
      • Permissible suction head (hS): +1,5 m
    • Nominal Plant Output: 10.148 kw
    • Max. Plant Output: 10.454 kw

Enter your keyword