- General Specification:
- Length: 10 km
- Type: Underground
- Passenger stations: 1
- Line capacity: 28,000 passengers per hour per direction
- Headway: 300 sec.
- Main equipment:
- Signaling system
- Communication system
- Control & SCADA
- Power supply included:
- PP: 2 units
- Lighting & power substations (LPS): 7 units
- Ventilation
- Fire alarm system
- Fire extinguishing system
- DWP (De-watering pumps)
Project Info
- Client: Islamic Republic of Iran Railways
- Main Contractor: Farab
- Location: Tehran, Iran
- Scheme: EPC
- Scope: Electromechanical equipment
- Progress: Under construction
Role of Farab Construction Co.
- Installation of electromechanical equipment