Gavoshan hydro power plant
Project Info
-
Client:
Regional Water Company of Kermanshah
-
Main Contractor:
Farab
-
Location:
Kermanshah, Iran
-
Scheme:
EPC
-
Scope:
Electromechanical & hydromechanical equipment, power house civil works
-
Progress:
Under construction
- Specification:
- Capacity: 4.6 MW (2 Units of 2.3 MW)
- Type of power house: Surface
- Main equipment:
- Turbine: Horizontal Francis
- Generator: Synchronous type, 6.3 KV
- Butterfly valve: Flange type, 1.4 m and 0.8 m inner outlet diameter
- Governor: Digital electrohydraulic governors, 70 bar
- Transformer: Oil type transformers, 1.1 MVA and 3.9 MVA
- Hydraulic steel structure: Only maintenance stoplogs