Gavoshan hydro power plant

Project Info
  • Client: Regional Water Company of Kermanshah
  • Main Contractor: Farab
  • Location: Kermanshah, Iran
  • Scheme: EPC
  • Scope: Electromechanical & hydromechanical equipment, power house civil works
  • Progress: Under construction
  • Specification:
    • Capacity: 4.6 MW (2 Units of 2.3 MW)
    • Type of power house: Surface
    • Main equipment:
      • Turbine: Horizontal Francis
      • Generator: Synchronous type, 6.3 KV
      • Butterfly valve: Flange type, 1.4 m and 0.8 m inner outlet diameter
      • Governor: Digital electrohydraulic governors, 70 bar
      • Transformer: Oil type transformers, 1.1 MVA and 3.9 MVA
      • Hydraulic steel structure: Only maintenance stoplogs

Enter your keyword