Project Info
  • Client: Iran Water & Power Resources Development Co.
  • Main Contractor: Farab
  • Location: Tehran, Iran
  • Scheme: EPC
  • Scope: Electromechanical & hydromechanical equipment
  • Progress: Completed
  • Capacity: 47 MW (2 Units of 23.5 MW)
  • Type of power house: Underground
  • Average annual power generation: 152.4 GWh
  • Main equipment:
    • Turbine: Vertical Francis, 750 rpm
    • Generator: Synchronous type, 11 KV
    • Inlet valve: Spherical, 1 m inner outlet diameter
    • Governor: Digital type with digital backup governors, 100 bar
    • Transformer: Three phase step up transformers, 27 MVA
    • Switchyard: 230 KV