Parsian gas turbine power plant

portfolio
portfolio
Project Info
  • Client: Iranian Gas Engineering & Development Co.
  • Main Contractor: Farab
  • Location: Fars, Iran
  • Scheme: EPC
  • Scope: Electromechanical equipment
  • Progress: Completed
  • Specification:
    • Capacity at ISO conditions: 120 MW (4 Units of 30 MW)
    • Fuel type: Natural gas
    • Substation: 20 KV, 11 KV

Role of Nardis Energy Projects Co.

  • Design, procurement and installation of gas pressure reduction station

Role of Farab Construction Co.

  • Civil works
  • Installation of electromechanical equipment, precommissioning and commissioning

Role of Farab Operations and Maintenance Co.

  • Equipment maintenance