Project Info
  • Client: Iran Water & Power Resources Development Co.
  • Main Contractor: Farab
  • Location: Mazandaran, Iran
  • Scheme: EPC
  • Scope: Electromechanical & hydromechanical equipment
  • Progress: Completed
  • Specification:
    • Capacity: 13.5 MW (3 Units of 4.5 MW)
    • Type of power house: Surface
    • Average annual power generation: 31 GWh
    • Main equipment:
      • Turbine: Vertical Francis, 750 rpm
      • Generator: Synchronous type, 6.3 KV
      • Inlet valve: Spherical, 0.8 m inner outlet diameter
      • Governor: Digital type backup governors, 80 bar
      • Transformer: Three phase step up transformers, 10 MVA, 63/6.3 KV