Shahid Rajaee hydro power plant
Project Info
-
Client:
Iran Water & Power Resources Development Co.
-
Main Contractor:
Farab
-
Location:
Mazandaran, Iran
-
Scheme:
EPC
-
Scope:
Electromechanical & hydromechanical equipment
-
Progress:
Completed
- Specification:
- Capacity: 13.5 MW (3 Units of 4.5 MW)
- Type of power house: Surface
- Average annual power generation: 31 GWh
- Main equipment:
- Turbine: Vertical Francis, 750 rpm
- Generator: Synchronous type, 6.3 KV
- Inlet valve: Spherical, 0.8 m inner outlet diameter
- Governor: Digital type backup governors, 80 bar
- Transformer: Three phase step up transformers, 10 MVA, 63/6.3 KV