Successful Synchronization of the third unit of Sardasht HPP with The National Power Grid

Successful Synchronization of the third unit of Sardasht HPP with The National Power Grid

The third and also Last unit of 150MW Sardasht Hydro Power Plant in West Azerbaijan was successfully synced with the national power grid on Saturday, 12th of Oct, 2019.

According to Public Relations of Farab Co., 150MW Sardasht Hydro Power Plant has 3* 50MW units with 422GW power generation capacity per year.

The first unit of this Hydro Power Plant on 25th of July, and The second unit of this HPP on 26th of Aug, 2019 were successfully synced with the national power grid.

Sardasht Hydro Power Plant and dam project is constructed in West Azerbaijan province, 15Km of Sardasht. The purpose of this project is to control surface and boundary waters, supply Sardasht and Rabat with agricultural and drinking water, exploit hydroelectric potential of runoffs by constructing a 150MW Power Plant, and create job opportunities during construction and operation, development and prosperity of tourism in the region.

Farab Co. is the contractor of Sardasht HPP.

 

 